What is a key deliverable of the Realize phase?

Prepare for the SAP S/4HANA Cloud, Private Edition Implementation with SAP Activate exam with flashcards and multiple-choice questions, complete with hints and detailed explanations. Ace your certification test!

The Realize phase in the SAP Activate framework is primarily focused on configuring the solution in accordance with the outcomes of previous workshops. During this phase, teams take the requirements gathered from stakeholders and workshops and translate them into specific configurations and customizations within the SAP S/4HANA system. This is crucial as it ensures that the system is tailored to meet the unique needs of the organization while aligning with business processes.

The emphasis on configuration based on workshop outcomes highlights the collaborative nature of this phase, where input from users and other stakeholders directly influences how the solution is set up. This ensures that the final system not only functions effectively but also supports the business objectives and user requirements, making it a key deliverable of the phase.

Other options, while relevant to the overall project, don't capture the core focus of the Realize phase as specifically as the correct answer. The complete deployment of the solution is typically the outcome of the subsequent phase, and the development of user training materials, while important, follows the configuration and realization of the system. Likewise, identification of key project stakeholders is more relevant to earlier phases of the project, particularly during the Prepare phase, rather than the direct activities happening during Realize.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy